Last month, Daily RFT spoke to Jim Woodward the man in charge of operations for the largest federal courthouse in the nation -- the 29-story Thomas F. Eagleton U.S. Courthouse (right). At the time, Woodward was working with contractors to determine the cost to repair flood damage after a pipe on the 17th floor came loose in August, sending an estimated 8,000 gallons of water cascading through the building. Today seven of the building's sixteen courtrooms are out of operation with excessive water damage.

In September, Woodward estimated the costs to clean up and fix the mess could reach $6 million. Turns out that was a conservative guess. Yesterday the federal government's General Services Administration, which owns the building, announced that the bill will be closer to $10 million to repair the damage.

A contractor fired during the construction of the building in the late 1990s is being blamed for improperly installing the pipe. It's unclear now whether the GSA will seek legal action against the construction company.

Support Local Journalism.
Join the Riverfront Times Press Club

Local journalism is information. Information is power. And we believe everyone deserves access to accurate independent coverage of their community and state. Our readers helped us continue this coverage in 2020, and we are so grateful for the support.

Help us keep this coverage going in 2021. Whether it's a one-time acknowledgement of this article or an ongoing membership pledge, your support goes to local-based reporting from our small but mighty team.

Join the Riverfront Times Club for as little as $5 a month.